As my previous post may have indicated, we became focused on heavy processes around software development and project management. We tried to manage these processes around tools. We did have moderate success around projects. However, we also had some fantastic failures. Here were some early observations that I had with those projects. At the time, I didn't know how to resolve them but I was able to find some interesting patterns. Here is the list of my top 10:
1) Traditional Waterfall assumes that you can figure out as much as possible early in the process. What's ironic is that we also understood the Cone of Uncertainty, which states that the reliability of estimates will become greater as you move through the process. We learned that we couldn't plan or predict the unexpected. We could prepare somewhat through risk management but not necessarily prevent things from happening.
2) Shorter range projects (less than 6 months) were more successful in meeting deadlines than larger range projects. It seemed the larger the project the harder it was to stay on track.
3) Projects that involved internal resources outside of the Development group were more successful than projects that didn't. These resources included Sales, Marketing, Technical Support, Customer Training, etc.
4) Projects that involved some interaction with outside customers were more successful than solely internal representatives.
5) Changes were harder and more resistant to make later in the process because it meant reinvesting a lot of time going upstream in the process. The process assumed that you wouldn't have to do a lot of that. Because of this, we would deliver functionality that the customer really wanted something different with the promise that we would look at it in the future (but rarely did).
6) Because of that, customers and/or customer representatives would ask for anything they could think of whether or not they really needed it because there was no other opportunity to do so.
7) Most of the projects involved managers who felt they had to have control over the project - control over what each resources worked on, control over what the customers could have, control over what stakeholders should know. However, on those rare projects where the manager was more transparent, more accommodating, and empowered the team to determine how they do the work and what work they should do; we found that everybody was happier, more motivated and produced better results.
8) Tools to manage projects became harder to use because it assumed that the work breakdowns, dependencies, resources allocated would hardly change and that the only thing that would change is time. That was rarely the case, and project managers found themselves managing the tool instead of the project itself.
9) It was assumed that estimates were reliable from those that provided it. Therefore, all milestones were expected to be hit by the stakeholders even though how we had figured out the milestones was very uncertain. Projects that were similar to those in the past fared better than those that were different. Most projects fell into the latter category and involved either domain or technical experience that was new to at least one member of the team at any time.
10) Though we had documentation for things such as requirement specification, technical design, etc, we found that as the process moved along those didn't reflect reality. It became too time consuming for people to go back to the documents. Therefore, the working solution and code behind it were the only thing that people could count on. We had thought that documentation were be used as a reference for future projects, but instead weren't used. Also, the documentation wasn't always developed by the team but many times passed around. Therefore, there were many disconnects because of misinterpretation of the documentation. These disconnects caused many of the bugs and incorrect solutions that caused much fix and test cycles as well as go back and fix the incorrect solutions sometime after the solution has been provided to the customer through a production release.
Even though we saw these patterns, and knew that something was wrong with our processes and approach to both software development and project management, we assumed that we were using the processes or tools wrong. It took us some time to finally figure out that perhaps the processes and tools were the culprit.
We started to look around to see if others were experiencing the same thing. And, that's how we discovered Agile...
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment